🏘️ Sewer Extensions for Developers

New subdivisions, commercial sites, and resorts that need public sewer.

Any sewer main, force main, lift station, or similar line that will connect to the District’s system, other than one building’s own service line, is a sewer extension. Sewer extensions must be designed by a Missouri-licensed professional engineer and approved by the District before construction. Start with a call: the earlier we talk, the fewer surprises later.

📞 Call (417) 544-0655

Extension or Connection Permit?

🏠

Connection Permit

One building connecting its own service line to an existing District sewer.

🚰 Connecting to Central Sewer →
🏘️

Sewer Extension Approval

A new sewer main, lift station, or force main, or a line serving two or more buildings.

📋 See the approval process ↓

The Approval Process

  1. Pre-Submittal Meeting

    Bring a preliminary plat, site plan, or aerial. We’ll discuss capacity, the approval path, whether a DNR construction permit is needed, and who will own each piece of infrastructure. Applications are accepted only after this meeting.

  2. Capacity Analysis and Will Serve Letter

    Submit the Capacity Analysis Application with preliminary plans and design flows. A District consulting engineer checks downstream capacity at the developer’s expense. If capacity is available, we issue a Will Serve Letter. If upgrades are needed, a Development Agreement sets the terms, and the developer generally pays for them. Proposals for low-pressure (grinder pump) systems also need a 20-year cost comparison with gravity sewer unless the District waives it.

  3. Plan Review

    Submit the Sewer Extension Application with plans, specifications, and an engineering report. Address review comments and obtain the District’s acknowledgment for your DNR submittal.

  4. Board Concept Approval When required

    Major subdivisions and projects with a Development Agreement go to the Board of Trustees. Submit complete materials at least two weeks before the meeting.

  5. DNR Construction Permit

    Obtain a Missouri DNR construction permit, or DNR’s written determination that one isn’t needed.

  6. Final Approval and Decision of Record

    Submit final signed and sealed documents, the DNR permit, and a construction cost estimate. Pay the inspection fee and sign the Decision of Record, which sets the terms for construction and acceptance. Capacity is reserved for five years.

  7. Construction and Inspection

    Hold a preconstruction meeting. Give our inspector 24 hours’ notice; all work must be inspected before it’s covered.

  8. Testing and Acceptance

    Submit certified test results, a transfer of assets agreement, recorded easements, PDF record drawings, and GIS shapefiles. The District then owns and maintains the public sewer, and the developer warrants the work for one year.

✅ After acceptance, each building connects with its own Connection Permit and capacity fee.

Costs at a Glance

ItemCost
Capacity analysis and plan review Billed to the developer by the District’s consulting engineer at hourly rates
System upgrades (if needed) Developer’s cost under a Development Agreement, paid before the project proceeds
Inspection fee 5% of the estimated sewer construction cost, paid before construction
Capacity fees $1,500 per residential unit; $7.40 per gallon per day of estimated flow for non-residential (Exhibit A), paid with each Connection Permit
Contractor requirements General liability insurance and a $5,000 utility/permit bond in the District’s name
🔒

Private Sewer Systems

When every building served is on one property held by one owner or association, the District may allow the extension to remain private. Private systems must meet the same design, inspection, testing, and fee requirements, and the owner is responsible for them permanently. Lines that serve separately owned lots, cross property lines, or run in public roads must be built as public sewer.

🏙️

Connecting to a City System?

If your project is in the unincorporated area of the county and will connect to a city’s sewer system and not the District’s, contact that city first. Different requirements may apply (Rules, Rates, and Regulations, Section 4.06).

📄

Forms & Standards

Applications, regulations, and design standards for sewer extensions

📜 Rules, Rates, and Regulations (Article IV)

📖 View PDF

📐 Capacity Analysis Application

🖨️ Print Form

📏 Sewer Extension Application

🖨️ Print Form

📐 Standard Details (Rev. July 2026)

📖 View PDF

📘 Standard Technical Specifications (Rev. August 2026)

📖 View PDF

✅ Development Check List (Exhibit B)

📖 View PDF

Ready to start? Call to schedule a pre-submittal meeting.

📞 Call (417) 544-0655