🚰 Connecting to Central Sewer

Connection Permits for new buildings, reconnections, and septic-to-sewer conversions.

A District Connection Permit is required before anyone installs, connects, reconnects, or relocates a service line or grinder pump on a District sewer. The permit makes sure your line is built right the first time and protects your neighbors’ service too.

📏

Is Sewer Required at My Property?

If a District sewer is within 300 feet of your property line, District regulations require you to connect within 90 days of written notice. Your septic tank must then be pumped, drained, filled with gravel, and abandoned.

🗺️ Find the sewer near you on the GIS Sewer Map →

Steps to Connect

  1. Find your sewer

    Use the GIS Sewer Map and call us to confirm the sewer type at your property: gravity, low-pressure (grinder pump), or a septic-tank system (STEG in Lakeway, STEP in Emory Creek).

    🗺️ GIS Sewer Map →
  2. Apply

    Submit a Connection Permit Application with proof of ownership (deed or tax statement) and a site plan drawn on a GIS map printout. Show the building, service line route, cleanouts, valves, any grinder pump or tank, and water and electric lines. Non-residential properties on private wells need a District-approved water meter before a permit is issued.

    🖨️ Connection Permit Application →
  3. Pay the capacity fee

    $1,500 per home or residential unit. Non-residential fees are based on estimated flow at $7.40 per gallon per day. Fees are waived during a District capital project and for one year after it is substantially complete.

  4. Pre-construction meeting

    You (or your representative), your contractor, and District staff review the requirements and lay out the route. The permit is then issued; post it on the property.

  5. Build and call for inspection

    Give us 24 hours’ notice. District staff must see the entire line before it’s backfilled, witness the pressure test, and be present when the main is tapped.

    📞 Call (417) 544-0655 →
  6. Set up billing

    Submit a Central Sewer Billing Application so your account can be set up.

Key Requirements for Contractors

⬇️ Gravity lines

Schedule 40 PVC; 4-inch minimum for homes, 6-inch for commercial; 1% minimum slope; cleanouts within 5 feet of the building and every 100 feet.

⚙️ Pressure lines

Owner-supplied grinder pump with an alarm, located outside the building; 1¼-inch Schedule 80 PVC or CTS; shutoff and check valves near the main.

🧰 All lines

18 inches minimum cover, No. 12 trace wire, and an air pressure test held for 15 minutes (5 psi gravity, 50 psi pressure).

🏠 One building, one service line

Exceptions require District approval.

🛡️ Contractors

Must carry general liability insurance and a $5,000 utility/permit bond in the District’s name.

📅 Permits

Are valid for one year from approval.

🔑 After connection

The owner owns and maintains the service line, its connection to the main, and any grinder pump.

Full requirements: Rules, Rates, and Regulations, Section 2.07, and the District’s Standard Details.

Common Questions

Can I connect an RV?

One RV may connect to your existing service line without an extra monthly charge if it isn’t used as a permanent residence. Additional RVs need a permit, capacity fee, and monthly charge.

Can my house and shop share a line?

Usually not. Each building needs its own service line unless the District approves an exception.

Who installs the line?

You hire a qualified contractor, and the District inspects the work. During District capital projects, the District installs the connection.

⚠️

Call 811 before you dig.

Missouri law requires it, and it’s free.